Return to KLUBNL.PL main page

rsgb_lf_group
[Top] [All Lists]

LF: RE: RE: 500Khz Nov

To: <[email protected]>
Subject: LF: RE: RE: 500Khz Nov
From: "Martyn Kinder" <[email protected]>
Date: Mon, 23 Jul 2007 21:15:57 +0100
Delivered-to: [email protected]
In-reply-to: <002601c7cd42$4d77c920$7f01a8c0@acer5gi5q0ubzj>
References: <[email protected]> <002601c7cd42$4d77c920$7f01a8c0@acer5gi5q0ubzj>
Reply-to: [email protected]
Sender: [email protected]
Thread-index: AcfNQn8g1iFO/VwjSiC96bCWFku8eAAI5qyw
Thread-topic: RE: 500Khz Nov
Hi all,

Mine was delayed because I didn't mention how I was goiung to control
frequency and power - too much of a rush to get off on my holidays...

No one at fault except myself...  :-)

Now I need to do some building..

Martyn 

-----Original Message-----
From: [email protected]
[mailto:[email protected]] On Behalf Of John W Gould
Sent: Monday, July 23, 2007 4:58 PM
To: [email protected]
Subject: LF: RE: 500Khz Nov

Paul, we put the page up at 

http://www.rsgb-spectrumforum.org.uk/ofcom_501kHz_%20srp.htm

to help with the applications.  RSGB assists Ofcom with the approval
process and what we are looking for is an indication of how one is going
to control the transmit frequency and ERP within the NoV conditions.
Unfortunately, the standard SRP form that Ofcom uses is slightly
misleading as it is really a form that was designed for other purposes,
such as high ERP systems that might cause RFI.  

Normally, applications can be turned around in less than 2 weeks - I
think Martyn's application may have been delayed because I was on
holiday, thus was waiting for my input.

73 John, G3WKL
RSGB HF Manager
[email protected]

-----Original Message-----
From: Martyn Kinder [mailto:[email protected]] On
Behalf Of Martyn Kinder
Sent: 23 July 2007 16:27
To: [email protected]
Subject: RE: 500Khz Nov



I have just got mine back.

I detailed all the ERP calculations.
I provided a plan of the house showing the aerial and cap wires. They
want to know how you will maintain frequency stability (XTAL control and
measured against GPS locked counter sufficed)and also ERP measurements
(Measure aerial current suffices) Took just over 2 weeks

GL

Martyn
==

Martyn Kinder LRPS G0CZD

http://www.czd.org.uk
P  Please consider the environment - do you really need to print this
email?

There are 10 types of people in the world - those who understand Binary
and those who don't...



-----Original Message-----
From: [email protected] on behalf of Paul T Middlehurst
Sent: Mon 2007-07-23 09:47
To: [email protected]
Subject: LF: 500Khz Nov
 
All

I am just about to complete a NOV for 500 KHz, any help or guidance
would be greatly appreciated.

 

TX just about built, thinking about an antenna at the moment!  

 

Regards & 73

 

Paul - G1DVA

 


No virus found in this outgoing message.
Checked by AVG Free Edition. 
Version: 7.5.476 / Virus Database: 269.10.14/912 - Release Date:
22/07/2007
19:02
 






<Prev in Thread] Current Thread [Next in Thread>